Management and Budget Department
Management and Budget Department

Monthly Capital Improvements Project Report
  
  

  

  

  

  

Click photo to enlarge
SPA 2 WRF INITIAL CAPACITY - 2 MGD
LAST UPDATED: 11/9/2009
PROJECT20609
DEPARTMENTPUBLIC WORKS - UTILITIES
PROJECT MANAGERGene Leap
CONTACT NUMBER623.695.1980
ADDRESS/LOCATION15667 W. Planada Lane
PROJECT DESCRIPTION
This project consists of a two million gallon per day (MGD) Modular Design Water Reclamation Facility (WRF) for Special Planning Area (SPA) 2. The Location is 15667 W. Planada Lane. This project will increase the overall SPA 2 capacity from 1.2 MGD to 3.2 MGD and will facilitate the ultimate phased build out of 12 MGD.
SCHEDULE PROGRESS
Design Procurement Council - Design Design Construction Procurement Council - Construction Construction
 
SCHEDULE BREAKDOWN
 
Delivery Method:   Construction Manager @ Risk (CM@R)
PROJECT PHASES PERCENT COMPLETE ORIGINAL EST COMPLETION PROJECTED COMPLETION PROCUREMENT RESULTS
 
Design Procurement 100 % 3/6/2006 8/14/2008
 
Council - Design Complete 8/1/2008 Carollo Engineers - $2,300,936
 
Design 100 % 1/1/2007 6/30/2009 PCL Contractors Pre-construction Services - $149,358
 
Construction Procurement 100 % 5/1/2007 5/28/2009
 
Council - Construction Complete 4/23/2009 PCL Contruction, Inc. CMAR $21,759,900
 
Construction 20 % 6/1/2009 2/1/2011
BUDGET BREAKDOWN
FUNDING SOURCE Sewer System Dev Fee, Pre-Paid by Developers
 
PROJECTED BUDGET Original $20,000,000.00
 
Change $7,865,900.00
 
Amended $27,865,900.00
 
TOTAL EXPENDED $8,294,232
 
BUDGET NOTES
Budget increase of $27,200,000 July 06. Budget increase of $7,080,000 July 07. Budget decrease of $23,388,300. Budget decrease of $3,025,800 Aug 08. Developer funding all costs up front. Budget - FY07 - $2,217,800, FY08 - $849,100, FY09 - $2,338,500, FY10 - $22,460,500.
PROJECT UPDATE
CURRENT PROJECT STATUS
Aeration basin wall segments 7 B&C, 6 B&C and 5 B&C have been poured. Wall segment 2 B&C are being formed. Backfill was placed along the east wall of the aeration basin. The membrane basin slabe on grade, north wall and segments a,b,c & d were poured. The base of the influent pump station and two barrels have been coated, set and backfilled. The conduit for Arizona Public Service (APS) power and Qwest communication has been installed. Contractor began drilling vadose well #4. Membrane blowers and compressors were delivered and stored.
 
WHAT'S NEXT
Aeration basin wall segments 2 C&B are being formed to pour early November. Work continues on wall segments, 3 C&B and 4 C&B. Work on the inlet channel wall segments is scheduled for completion in November. Work will begin to extend the 8-inch water main into the plant area. Drilling the vadose wells will continue.
        
 