Home
|
Events Calendar
|
Careers
|
Archive Center
Translate this page
中国
中國
日本語
Deutsch
Español
Français
Italian
Home
|
Print
|
RSS
Proposed FY2010 Budget
FY2009 Budget
FY 2009 - 2013 Capital Improvement Plan
Monthly Capital Improvement Report
You are here:
Home
>
City Departments
>
Management and Budget
>
Annual Budget / Capital Improvement Plan
>
Monthly Capital Improvement Reports
Monthly Capital Improvements Project Report
Click photo to enlarge
SPA 2 WRF INITIAL CAPACITY - 2 MGD
LAST UPDATED:
8/2/2010
PROJECT
20609
DEPARTMENT
PUBLIC WORKS - UTILITIES
PROJECT MANAGER
Gene Leap
CONTACT NUMBER
623.695.1980
ADDRESS/LOCATION
15667 W. Planada Lane
PROJECT DESCRIPTION
This project consists of a two million gallon per day (MGD) Modular Design Water Reclamation Facility (WRF) for Special Planning Area (SPA) 2. The Location is 15667 W. Planada Lane. This project will increase the overall SPA 2 capacity from 1.2 MGD to 3.2 MGD and will facilitate the ultimate phased build out of 12 MGD.
SCHEDULE PROGRESS
Design Procurement
Council - Design
Design
Construction Procurement
Council - Construction
Construction
SCHEDULE BREAKDOWN
Delivery Method:
Construction Manager @ Risk (CM@R)
PROJECT PHASES
PERCENT COMPLETE
ORIGINAL EST COMPLETION
PROJECTED COMPLETION
PROCUREMENT RESULTS
Design Procurement
100
%
3/6/2006
8/14/2008
Council - Design
Complete
8/1/2008
Carollo Engineers - $2,300,936
Design
100
%
1/1/2007
6/30/2009
PCL Contractors Pre-construction Services - $149,358
Construction Procurement
100
%
5/1/2007
5/28/2009
Council - Construction
Complete
4/23/2009
PCL Contruction, Inc. CMAR $21,759,900
Construction
90
%
6/1/2009
2/1/2011
BUDGET BREAKDOWN
FUNDING SOURCE
Sewer System Dev Fee, Pre-Paid by Developers
PROJECTED BUDGET
Original
$20,000,000.00
Change
$7,865,900.00
Amended
$27,865,900.00
TOTAL EXPENDED
$25,933,379
BUDGET NOTES
Budget increase of $27,200,000 July 06. Budget increase of $7,080,000 July 07. Budget decrease of $23,388,300. Budget decrease of $3,025,800 Aug 08. Developer funding all costs up front. Budget - FY07 - $2,217,800, FY08 - $849,100, FY09 - $2,338,600, FY10 - $19,021,400, FY11 - $3,439,000.
PROJECT UPDATE
CURRENT PROJECT STATUS
Loop checks and functional testing on the aeration basin mixers and blowers are complete. Loop checks have been completed on the rotary drum screens, membrane motor operated valves, permeate pumps flow indicators and chemical tote scales. The Zenon representative is on-site checking the membrane control system and assisting with equipment loop checks and functional testing. Wires continue to be pulled and terminated at the ultraviolet disinfection system, feed forward pumps, influent pump station, and permeate pumps. Discharge pipe is being installed at the influent pump station. Area light bases have been poured and wires pulled. The shade structure bases have been poured.
WHAT'S NEXT
Equipment loop checks and functional testing is on-going. Painting is on-going. The shade structures are due for delivery and installation in August. Site grading is being staked out for final grade. A flush line will be installed on the vadose wells in August. The 7-day water test is scheduled for the end of August contingent on the receipt of the Aquifer Protection Permit from the Arizona Department of Environmental Quality and an Approval to Commence Operations from Maricopa County.
16000 N. Civic Center Plaza Surprise, AZ 85374 Phone: 623.222.1000 TTY: 623.222.1002 /
Phone Directory
Questions or Comments
contact the Webmaster@surpriseaz.com
Privacy Statement
|
Accessibility
|
Copyright Notices
| Powered by
CivicPlus