Monthly Capital Improvements Project Report
|
|
Click photo to enlarge |
|
DYSART ROAD & THUNDERBIRD INTERSECTION IMPROVEMENTS
|
| LAST UPDATED: |
8/4/2010
|
| PROJECT | 20632 |
| DEPARTMENT | TRANSPORTATION |
| PROJECT MANAGER | Jeff Davidson |
| CONTACT NUMBER | 623.222.6130 |
| ADDRESS/LOCATION | Dysart and Thunderbird |
PROJECT DESCRIPTION
The project will be designed and constructed by the City of El Mirage. It is the construction of a two-lane signalized intersection. City of Surprise will share the cost with the City of El Mirage. The budgeted amount will be reimbursed by the City of Surprise as per an Intergovernmental Agreement.
|
|
|
|
|
SCHEDULE PROGRESS |
|
Design Procurement |
Council - Design
|
Design |
Construction Procurement |
Council - Construction |
Construction |
|
|
|
|
|
|
|
|
|
|
SCHEDULE BREAKDOWN |
Delivery Method:
Design - Bid - Build |
|
|
PROJECT PHASES |
PERCENT COMPLETE |
ORIGINAL EST COMPLETION |
PROJECTED COMPLETION |
PROCUREMENT RESULTS |
|
|
|
Design Procurement |
100
% |
12/1/2006 |
12/1/2006 |
|
|
|
|
Council - Design |
N/A
|
|
|
|
|
|
|
Design |
100
% |
6/1/2007 |
6/30/2009 |
Wood Patel by City of El Mirage. |
|
|
|
Construction Procurement |
100
% |
12/1/2007 |
9/30/2009 |
DCS Contracting for $1.8 million |
|
|
|
Council - Construction |
N/A
|
|
|
|
|
|
|
Construction |
90
% |
12/1/2008 |
12/15/2010 |
|
|
|
|
|
|
|
|
|
|
FUNDING SOURCE |
Transportation Improvement |
|
|
|
PROJECTED BUDGET |
Original |
$1,200,000.00 |
|
|
|
|
Change |
$1,120,000.00 |
|
|
|
|
Amended |
$2,320,000.00 |
|
|
|
TOTAL EXPENDED |
|
$743,150 |
|
|
BUDGET NOTES
Budget increase of $120,000 July 06. Budget increase of $1,000,000 July 09.
Budget - FY10 - $743,200, FY11 - $1,576,800
|
|
|
|
|
CURRENT PROJECT STATUS
Final striping and the final installation of a few additional railway crossing devices are all that remain of the project. The railway crossing devices may not be necessary if BNSF decides the intersection does not warrant the devices. |
WHAT'S NEXT
The final roadway striping is scheduled to be completed in August. |
|
|