FY2009 Budget
FY 2009 - 2013 Capital Improvement Plan
Monthly Capital Improvement Report
You are here:
Home
>
City Departments
>
Management and Budget
>
Annual Budget / Capital Improvement Plan
>
Monthly Capital Improvement Reports
Monthly Capital Improvements Project Report
Click photo to enlarge
FIBER OPTICS - GREENWAY ROAD (GRAND AVENUE TO COTTON LANE)
LAST UPDATED:
11/10/2009
PROJECT
20718
DEPARTMENT
TRANSPORTATION
PROJECT MANAGER
Brian Moberly
CONTACT NUMBER
623.222.1733
ADDRESS/LOCATION
Greenway Road: Grand Avenue to Cotton Lane
PROJECT DESCRIPTION
Design and installation/construction of fiber optics for the connection of traffic signals, CCTV (Closed Circuit Television) cameras, and changeable message signs. Greenway Road, from Grand Avenue to Cotton Lane, was proposed for MAG (Maricopa Association of Governments) funding requested for FY2008, but received MAG approval for FY2010.
SCHEDULE PROGRESS
Design Procurement
Council - Design
Design
Construction Procurement
Council - Construction
Construction
SCHEDULE BREAKDOWN
Delivery Method:
Design - Bid - Build
PROJECT PHASES
PERCENT COMPLETE
ORIGINAL EST COMPLETION
PROJECTED COMPLETION
PROCUREMENT RESULTS
Design Procurement
100
%
2/28/2007
9/30/2007
Council - Design
Complete
9/1/2007
9/13/2007
Kimley-Horn & Associates - $250,000
Design
98
%
12/30/2007
1/15/2010
Construction Procurement
0
%
3/31/2008
1/14/2010
Council - Construction
Pending
1/15/2010
Construction
0
%
12/30/2008
6/1/2010
BUDGET BREAKDOWN
FUNDING SOURCE
Public Works Development Fee
PROJECTED BUDGET
Original
$418,000.00
Change
$2,332,000.00
Amended
$2,750,000.00
TOTAL EXPENDED
$232,488
BUDGET NOTES
Budget increase of $332,000 July 07. Budget increase of $950,000 July 08. Budget increase of $1,050,000 July 09. Budget - FY08 - $137,500, FY09 - $75,000, FY10 - $37,500, FY15 - $2,500,000
PROJECT UPDATE
CURRENT PROJECT STATUS
Final plans and specifications have been submitted to Arizona Department of Tranportation's (ADOT) contracts and specifications section for review. FHWA has authorized funds for this project and a project manager for contracts and specifications has been assigned. Initial Intergovernmental Agreement (IGA) has been recieved and is under department review. Design final completion has been delayed awaiting ADOT approval.
WHAT'S NEXT
Review the IGA and submit to the city attorney's office. Finalize the bid package with the ADOT contracts and specifications group.
16000 N. Civic Center Plaza Surprise, AZ 85374 Phone: 623.222.1000 TTY: 623.222.1002 /
Phone Directory
Questions or Comments
contact the Webmaster@surpriseaz.com
Privacy Statement
|
Accessibility
|
Copyright Notices
| Powered by
CivicPlus