Management and Budget Department
Management and Budget Department

Monthly Capital Improvements Project Report
  
  

  

Click photo to enlarge
SCADA - UPGRADES - SYSTEM EXPANSION
LAST UPDATED: 11/10/2009
PROJECT20721
DEPARTMENTPUBLIC WORKS - UTILITIES
PROJECT MANAGERLee Lambert
CONTACT NUMBER623.222.7032
ADDRESS/LOCATIONCity Wide
PROJECT DESCRIPTION
Design and completion of the Master Supervisory Control and Data Acquisition (SCADA) system at Rancho Gabriela, Desert Oasis, Roseview Water Supply Facility, Ashton Ranch Water Supply Facility, and Mountain Vista Water Supply Facility. This is includes multiple phase upgrades and/or completion of any portion of the SCADA system not covered by previous funding. Design funding includes any unforeseen structural changes such as a radio tower. Construction funding includes computer hardware/software upgrades and security at the various sites.
SCHEDULE PROGRESS
Design Procurement Council - Design Design Construction Procurement Council - Construction Construction
 
SCHEDULE BREAKDOWN
 
Delivery Method:   Design - Bid - Build
PROJECT PHASES PERCENT COMPLETE ORIGINAL EST COMPLETION PROJECTED COMPLETION PROCUREMENT RESULTS
 
Design Procurement 100 % 5/1/2007 5/1/2007
 
Council - Design Complete 5/1/2007 5/1/2007 DLT&V - $148,558
 
Design 100 % 5/1/2008 7/1/2008
 
Construction Procurement 100 % 9/1/2006 11/1/2008
 
Council - Construction N/A
 
Construction 90 % 6/1/2007 11/30/2009
BUDGET BREAKDOWN
FUNDING SOURCE Water Operations, Water System Development Fee
 
PROJECTED BUDGET Original $250,000.00
 
Change $250,000.00
 
Amended $500,000.00
 
TOTAL EXPENDED $285,972
 
BUDGET NOTES
Budget increase of $100,000 July 07. Budget increase of $250,000 July 08. Budget transfer decrease of $100,000 Sept 08 to Roseview Arsenic project 20521. Budget - FY07 - $12,100, FY08 - $134,200, FY09 - $139,700, FY10 - $214,000.
PROJECT UPDATE
CURRENT PROJECT STATUS
We are finishing up the Roseview water supply facility and will essentially complete the first phase of construction for the SCADA system that originally started design in late 2005, with construction on a plant-by-plant basis starting in 2007 and continuing until now. The remaining Capital Improvement Program (CIP) money within this project is currently tied up as matching funds for an Environmental Protection Agency (EPA) Grant. Once the EPA has made a determination in November, these monies should become available again to proceed forward with the second phase of work. At this time, the completion date has been changed from October 2009 to November 2009 to reflect the the potential grant award.
 
WHAT'S NEXT
Once the CIP money becomes available, the City can move forward with a second phase of SCADA work for remote control of the plant sites (programming work primarily). In addition, we need to look at minor improvements to a couple of our sites and programming improvements to gather the data into useful reports used on a regular basis (such as daily chlorination reports).
        
 