SPA 1 16-IN RECLAIMED LINE - PARKVIEW & GREENWAY
LAST UPDATED:
7/29/2010
PROJECT
20726
DEPARTMENT
PUBLIC WORKS - UTILITIES
PROJECT MANAGER
Lee Lambert
CONTACT NUMBER
623.222.7032
ADDRESS/LOCATION
Greenway Rd. from Parkview Pl. to Reems Rd., Waddell/Litchfield Intersection
PROJECT DESCRIPTION
Design and construction of a 16 inch reclaimed water line and booster station. This project will expand the existing Litchfield Road reclaimed water line by 1.5 miles and deliver reclaimed water to the Dysart Unified School District, as well as provide a booster station to increase pressure and deliver reclaimed water to the Surprise Center area. The design for the reclaimed portion of this project is complete. Construction for the reclaimed lines are slated for FY16.
SCHEDULE PROGRESS
Design Procurement
Council - Design
Design
Construction Procurement
Council - Construction
Construction
SCHEDULE BREAKDOWN
Delivery Method:
Design - Bid - Build
PROJECT PHASES
PERCENT COMPLETE
ORIGINAL EST COMPLETION
PROJECTED COMPLETION
PROCUREMENT RESULTS
Design Procurement
100
%
8/1/2006
8/1/2006
Council - Design
N/A
Design
100
%
7/1/2007
7/30/2009
Brooks Engineering - $170,000.00
Construction Procurement
100
%
10/1/2008
11/30/2009
Council - Construction
Complete
10/1/2008
11/12/2009
Garney Construction Company - $1,315,000
Construction
75
%
6/1/2009
11/30/2010
BUDGET BREAKDOWN
FUNDING SOURCE
Replenishment System Development Fee
PROJECTED BUDGET
Original
$2,750,000.00
Change
$500,000.00
Amended
$3,250,000.00
TOTAL EXPENDED
$1,401,163
BUDGET NOTES
Budget increase of $500,000 July 07. Budget - FY07 - $103,400, FY08 - $47,300, FY09 - $33,700, FY10 - $196,700, FY11 - $1,368,900, FY16 - $1,500,000.
PROJECT UPDATE
CURRENT PROJECT STATUS
The booster station has been placed, and now the utilities are being connected to it. In addition, backfilling and compaction at the deeper levels have begun.
WHAT'S NEXT
We will complete the remaining utility connections and backfilling along with landscaping by the end of August. Testing the station will occur in September.
16000 N. Civic Center Plaza Surprise, AZ 85374 Phone: 623.222.1000 TTY: 623.222.1002 /
Phone Directory
Questions or Comments
contact the Webmaster@surpriseaz.com
Privacy Statement
|
Accessibility
|
Copyright Notices
| Powered by
CivicPlus