Monthly Capital Improvements Project Report
  
  

  

Click photo to enlarge
GREENWAY ROAD IMPROVEMENTS (LITCHFIELD ROAD TO BULLARD AVENUE)
LAST UPDATED: 11/6/2009
PROJECT20815
DEPARTMENTTRANSPORTATION
PROJECT MANAGERJeff Davidson
CONTACT NUMBER623.222.6131
ADDRESS/LOCATIONGreenway Road (Litchfield Road to Bullard Avenue)
PROJECT DESCRIPTION
Construction of new pavement, sidewalk, bike lane, curb, gutter, streetlights, landscaping, and turn lanes at every quarter mile. The improvements will include roadway improvements to the northern half of Greenway Road from Litchfield Road to Bullard Avenue to match the existing improvements to the east and west. Additional improvements include drainage, 12 inch sewer line, 16 inch reclaimed waterline, and Intelligent Transportation System (ITS) conduit.
SCHEDULE PROGRESS
Design Procurement Council - Design Design Construction Procurement Council - Construction Construction
 
SCHEDULE BREAKDOWN
 
Delivery Method:   Design - Bid - Build
PROJECT PHASES PERCENT COMPLETE ORIGINAL EST COMPLETION PROJECTED COMPLETION PROCUREMENT RESULTS
 
Design Procurement 100 % 11/30/2007 11/10/2007
 
Council - Design Complete 2/1/2008 1/10/2008 CMX - $250,000
 
Design 100 % 12/1/2008 3/30/2010 Project Placed on Hold.
 
Construction Procurement 0 % 1/1/2009 6/30/2010
 
Council - Construction Pending 3/1/2009 7/8/2010
 
Construction 0 % 6/1/2009 2/1/2011
PROJECT UPDATE
CURRENT PROJECT STATUS
Based on direction received from the Mayor and Council September 10th, this project has been placed on hold. Further direction from the Mayor and Council will be required to activate the funding.
 
WHAT'S NEXT
Staff awaits further direction from the Mayor and Council.
        
 