CIVIC CENTER PARKWAY (SOUTH OF BELL ROAD TO PARADISE LANE)
LAST UPDATED:
11/6/2009
PROJECT
20817
DEPARTMENT
TRANSPORTATION
PROJECT MANAGER
Jeff Davidson
CONTACT NUMBER
623.222.6131
ADDRESS/LOCATION
Civic Center Parkway (South of Bell Road to Paradise Lane)
PROJECT DESCRIPTION
Design and construction of new pavement, sidewalk, bike lane, curb, gutter, streetlights, turn lanes, Intelligent Transportation System (ITS) conduits, and landscaping. This project will complete Civic Center Parkway as a three lane road in each direction between Bell Road and Paradise Lane (a distance of approximately 2,100 feet). Additional improvements include drainage, signal modification at Bell Road, and a new signal at Paradise Lane.
SCHEDULE PROGRESS
Design Procurement
Council - Design
Design
Construction Procurement
Council - Construction
Construction
SCHEDULE BREAKDOWN
Delivery Method:
Design - Bid - Build
PROJECT PHASES
PERCENT COMPLETE
ORIGINAL EST COMPLETION
PROJECTED COMPLETION
PROCUREMENT RESULTS
Design Procurement
100
%
11/30/2007
11/10/2007
Council - Design
Complete
2/1/2008
1/10/2008
Dibble - $160,000
Design
100
%
12/1/2008
4/30/2009
Construction Procurement
0
%
1/1/2009
1/1/2010
Council - Construction
Pending
3/1/2009
3/11/2010
Construction
0
%
6/1/2009
12/6/2010
BUDGET BREAKDOWN
FUNDING SOURCE
Transportation Improvement
PROJECTED BUDGET
Original
$160,000.00
Change
$3,833,800.00
Amended
$3,993,800.00
TOTAL EXPENDED
$131,867
BUDGET NOTES
$160,000 budget transfer from Transportation Improvement Fund Development Reimbursements 01/10/08. Budget increase of $3,840,000 July 08. Budget decrease of $6,200 July 09. Budget - FY08 - $63,600, FY09 - $68,300, FY10 - $21,900, FY15 - $3,840,000
PROJECT UPDATE
CURRENT PROJECT STATUS
The 100% design plans, specifications and bid items are complete and ready for bidding.
WHAT'S NEXT
This project will be removed from the November report until construction funding is available.
16000 N. Civic Center Plaza Surprise, AZ 85374 Phone: 623.222.1000 TTY: 623.222.1002 /
Phone Directory
Questions or Comments
contact the Webmaster@surpriseaz.com
Privacy Statement
|
Accessibility
|
Copyright Notices
| Powered by
CivicPlus