Monthly Capital Improvements Project Report
  
  

  

  

  

  

  

  

  

  

Click photo to enlarge
BELL ROAD LANDSCAPING AND LIGHTING
LAST UPDATED: 11/9/2009
PROJECT20901
DEPARTMENTTRANSPORTATION
PROJECT MANAGERJeff Davidson
CONTACT NUMBER623.222.6131
ADDRESS/LOCATIONBell Road (114th Avenue to Beardsley Canal)
PROJECT DESCRIPTION
This project will provide landscaping within the medians along Bell Road from Avenue of the Arts (114th Avenue) to Beardsley Canal. A distance of nine miles. The existing median landscaping will be replaced with decomposed granite, or low water use plant materials. The landscaping design plans are complete. This project also includes purchase and installation of lighting along Bell Road from 114th Avenue (Avenue of the Arts)to Beardsley Canal.
SCHEDULE PROGRESS
Design Procurement Council - Design Design Construction Procurement Council - Construction Construction
 
SCHEDULE BREAKDOWN
 
Delivery Method:   Design - Bid - Build
PROJECT PHASES PERCENT COMPLETE ORIGINAL EST COMPLETION PROJECTED COMPLETION PROCUREMENT RESULTS
 
Design Procurement 100 % 9/1/2008 8/1/2008 Kittleson -$45,000, Waibel - $10,000
 
Council - Design N/A
 
Design 100 % 12/1/2008 3/1/2009
 
Construction Procurement 100 % 2/1/2009 4/9/2009
 
Council - Construction Complete 4/1/2009 4/9/2009 AR Mays Construction - $269,000
 
Construction 10 % 6/1/2014 6/1/2014
BUDGET BREAKDOWN
FUNDING SOURCE General Capital
 
PROJECTED BUDGET Original $8,908,900.00
 
Change $0.00
 
Amended $8,908,900.00
 
TOTAL EXPENDED $216,409
 
BUDGET NOTES
Budget - FY09-$161,400, FY10-$1,047,500, FY15-$1,000,000, FY16-$1,000,000, FY17-$1,000,000, FY18-$1,000,000, FY19 - $3,700,000
PROJECT UPDATE
CURRENT PROJECT STATUS
Construction on the gateway entry monument is nearly complete. The solar equipment that was ordered in September is the last to be installed. Arizona Public Service (APS) has ordered the streetlight poles which will be install the first of next year. The contract for the landscaping portion of the project was brought before Mayor and Council October 22nd, but was not approved. The Mayor and Council elected to address this portion of the project during the FY2011 budget process.
 
WHAT'S NEXT
APS will commence installation of the electrical conduit for the streetlights in November.
        
 