Monthly Capital Improvements Project Report
  
  

  

  

  

  

Click photo to enlarge
PARK AND RIDE
LAST UPDATED: 8/4/2010
PROJECT20909
DEPARTMENTPUBLIC WORKS - BUILDINGS
PROJECT MANAGERHarry Hartman
CONTACT NUMBER623.222.6000
ADDRESS/LOCATION13327 W. Bell Road
PROJECT DESCRIPTION
Regional Transportation Plan (RTP) of Maricopa Association of Governments (MAG) has outlined that a regional park and ride facility shall be in Surprise to serve existing and future transit routes along Bell Road and Grand Avenue. This project consists of site selection, land purchase, design and construction of a park and ride facility consisting of 230 parking spaces. Additional amenities may include passenger shelters, vertical shade screens, bicycle racks, and seating.
SCHEDULE PROGRESS
Design Procurement Council - Design Design Construction Procurement Council - Construction Construction
 
SCHEDULE BREAKDOWN
 
Delivery Method:   Design - Bid - Build
PROJECT PHASES PERCENT COMPLETE ORIGINAL EST COMPLETION PROJECTED COMPLETION PROCUREMENT RESULTS
 
Design Procurement 100 % 9/1/2008 9/1/2008
 
Council - Design Complete 9/1/2008 9/1/2008 TranSystems - $173,442
 
Design 100 % 3/1/2009 1/1/2010
 
Construction Procurement 100 % 6/1/2009 3/25/2010
 
Council - Construction Complete 6/1/2009 3/25/2010 Summit Builders - $1,212,000
 
Construction 45 % 1/1/2010 10/1/2010
BUDGET BREAKDOWN
FUNDING SOURCE Regional Public Transportation Authority, LTAF II
 
PROJECTED BUDGET Original $4,500,700.00
 
Change $151,000.00
 
Amended $4,651,700.00
 
TOTAL EXPENDED $2,004,099
 
BUDGET NOTES
Budget increase of $151,000 July 10. Budget - FY09 - $243,500, FY10 - $1,613,100, FY11 - $2,795,100 Regional Public Transportation Authority Contribution - $4,500,700, Local Transportation Assistance Fund II(LTAF II) - $151,000
PROJECT UPDATE
CURRENT PROJECT STATUS
The Park and Ride's curb and gutter and all underground plumbing and electrical was completed in July. The driver's restroom facility began to take shape with the erection of the walls and placement of the roof.
 
WHAT'S NEXT
August will see continued work on the parking lot itself. The lot's subgrade will be placed and paving should take place in near the end of the month. The restroom's finishes will also begin installation at the end of August.
        
 