Monthly Capital Improvements Project Report
|
|
|
|
JERRY STREET FLOOD DRAINAGE
|
| LAST UPDATED: |
11/10/2009
|
| PROJECT | 20913 |
| DEPARTMENT | TRANSPORTATION |
| PROJECT MANAGER | Suneel Garg |
| CONTACT NUMBER | 623.222.6130 |
| ADDRESS/LOCATION | Jerry Street between Ironwood Street and Ocotillo Street |
PROJECT DESCRIPTION
The project will consist of constructing an underground retention system within the future parking lot of the church property. The retention system will consist of 96 inch Corrugated Metal Pipes (CMP) and drywells. The retention system will convey to El Mirage Road which ultimately drains to the El Mirage Wash. This site is located on Jerry Street between Ironwood Street and Ocotillo Street. This location is a low point where storm water run-off accumulates with nowhere to go except to pond in the streets. As the water rises, local residences experience flooding. The completion of this project will eliminate the flooding concerns of local residents. The ponding problems will be relieved by providing positive drainage to El Mirage Road and possibly providing storm water retention.
|
|
|
|
|
SCHEDULE PROGRESS |
|
Design Procurement |
Council - Design
|
Design |
Construction Procurement |
Council - Construction |
Construction |
|
|
|
|
|
|
|
|
|
|
SCHEDULE BREAKDOWN |
Delivery Method:
Design - Bid - Build |
|
|
PROJECT PHASES |
PERCENT COMPLETE |
ORIGINAL EST COMPLETION |
PROJECTED COMPLETION |
PROCUREMENT RESULTS |
|
|
|
Design Procurement |
100
% |
3/31/2009 |
2/21/2009 |
RBF Consulting for $42,610 |
|
|
|
Council - Design |
N/A
|
|
|
|
|
|
|
Design |
100
% |
6/30/2010 |
6/30/2009 |
|
|
|
|
Construction Procurement |
0
% |
10/31/2010 |
10/31/2010 |
|
|
|
|
Council - Construction |
Pending
|
12/31/2010 |
12/23/2010 |
|
|
|
|
Construction |
0
% |
6/1/2011 |
6/1/2011 |
|
|
|
|
|
|
|
|
|
|
FUNDING SOURCE |
General Capital |
|
|
|
PROJECTED BUDGET |
Original |
$640,000.00 |
|
|
|
|
Change |
($300,000.00) |
|
|
|
|
Amended |
$340,000.00 |
|
|
|
TOTAL EXPENDED |
|
$ |
|
|
BUDGET NOTES
Project created Dec 2008. Budget transfer decrease of $300,000 Sept 09.
Budget - FY10 - $340,000 |
|
|
|
|
CURRENT PROJECT STATUS
The 100% designed construction documents are under review by city staff. |
WHAT'S NEXT
Staff met with the property owner located east of the church to discuss a drainage easement. The consultant will prepare the easement for the property owner's approval. |
|
|