Monthly Capital Improvements Project Report
|
|
|
|
ITS INFRASTRUCTURE AND LIGHTING ON SR 303
|
| LAST UPDATED: |
11/10/2009
|
| PROJECT | 20916 |
| DEPARTMENT | TRANSPORTATION |
| PROJECT MANAGER | Suneel Garg |
| CONTACT NUMBER | 602.222.6130 |
| ADDRESS/LOCATION | Loop 303 Cactus, Waddell and Bell Road |
PROJECT DESCRIPTION
Design and construction of conduit for the city’s future Intelligent Transportation System (ITS) Infrastructure and lighting administered by Arizona Department of Transportation (ADOT). Work will be performed on SR 303 at the intersections of Cactus Road, Waddell Road and Bell Road. Under an Intergovernmental Agreement (IGA), the city will reimburse ADOT for the above cost of design and construction.
|
|
|
|
|
SCHEDULE PROGRESS |
|
Design Procurement |
Council - Design
|
Design |
Construction Procurement |
Council - Construction |
Construction |
|
|
|
|
|
|
|
|
|
|
SCHEDULE BREAKDOWN |
Delivery Method:
Construction Manager @ Risk (CM@R) |
|
|
PROJECT PHASES |
PERCENT COMPLETE |
ORIGINAL EST COMPLETION |
PROJECTED COMPLETION |
PROCUREMENT RESULTS |
|
|
|
Design Procurement |
100
% |
2/26/2009 |
2/26/2009 |
ADOT under contract with Dibble Engineering |
|
|
|
Council - Design |
N/A
|
|
|
|
|
|
|
Design |
100
% |
|
|
|
|
|
|
Construction Procurement |
100
% |
|
|
|
|
|
|
Council - Construction |
Complete
|
5/28/2009 |
5/28/2009 |
IGA with ADOT was approved for the reimbursment. |
|
|
|
Construction |
5
% |
5/31/2011 |
5/31/2011 |
|
|
|
|
|
|
|
|
|
|
FUNDING SOURCE |
Transportation Improvement |
|
|
|
PROJECTED BUDGET |
Original |
$247,800.00 |
|
|
|
|
Change |
$0.00 |
|
|
|
|
Amended |
$247,800.00 |
|
|
|
TOTAL EXPENDED |
|
$247,755 |
|
|
BUDGET NOTES
Project created Feb 09.
Budget - FY09 - $247,800
|
|
|
|
|
CURRENT PROJECT STATUS
Based on the information provided by the Arizona Department of Transportation (ADOT), construction has begun. This project is administered by ADOT and constructed by Sundt Construction. |
WHAT'S NEXT
ADOT will construct the ITS and light improvements within the next 18 months. According to the ADOT schedule, the conduit will be installed in January 2010. |
|
|