Monthly Capital Improvements Project Report
|
|
|
|
RECLAIMED WATER LINE CONNECTION LITCHFIELD MANOR
|
| LAST UPDATED: |
5/6/2010
|
| PROJECT | 20917 |
| DEPARTMENT | PUBLIC WORKS - UTILITIES |
| PROJECT MANAGER | Tom McCullough |
| CONTACT NUMBER | 623.222.6000 |
| ADDRESS/LOCATION | Litchfield Road and Acoma Drive |
PROJECT DESCRIPTION
Design, permit, and construct the reclaim water connection for the Litchfield Manor Development that will allow their Homeowners Association (HOA) to use reclaim water for irrigating the common areas and landscaping thoughout the entire development.
|
|
|
|
|
SCHEDULE PROGRESS |
|
Design Procurement |
Council - Design
|
Design |
Construction Procurement |
Council - Construction |
Construction |
|
|
|
|
|
|
|
|
|
|
SCHEDULE BREAKDOWN |
Delivery Method:
Design - Bid - Build |
|
|
PROJECT PHASES |
PERCENT COMPLETE |
ORIGINAL EST COMPLETION |
PROJECTED COMPLETION |
PROCUREMENT RESULTS |
|
|
|
Design Procurement |
100
% |
3/12/2009 |
3/12/2009 |
|
|
|
|
Council - Design |
Complete
|
3/12/2009 |
3/12/2009 |
R.H. Dupper $24,405 |
|
|
|
Design |
100
% |
6/1/2009 |
8/15/2009 |
|
|
|
|
Construction Procurement |
100
% |
7/1/2009 |
9/18/2009 |
|
|
|
|
Council - Construction |
N/A
|
|
|
|
|
|
|
Construction |
100
% |
11/1/2009 |
4/30/2010 |
|
|
|
|
|
|
|
|
|
|
|
CURRENT PROJECT STATUS
The final connection testing was conducted in April. The reclaimed waterline is now providing reclaimed water to the common area landscaping in Litchfield Manor. The project is complete. |
WHAT'S NEXT
The project is complete. |
|
|