Management and Budget Department
Management and Budget Department

Monthly Capital Improvements Project Report
  
LOOP 303 SEWER AND IRRIGATION LINE
LAST UPDATED: 7/27/2010
PROJECT20918
DEPARTMENTPUBLIC WORKS - UTILITIES
PROJECT MANAGERMichael Boule/Fred Stevens
CONTACT NUMBER623.222.7040
ADDRESS/LOCATION 
PROJECT DESCRIPTION
Intergovernmental Agreement (IGA) with Arizona Department of Transportation (ADOT) for the design and relocation of sewer and irrigation lines that reside in the path of the Loop 303 at Bell Road and Cactus Road. ADOT will design and construct, the city is only required to pay their burden of relocation. Design will start as soon as the city provides ADOT with the upfront costs estimated by ADOT and signs the associated resolution. Actual construction will start shortly after design is complete but current date is unknown at this time. The project wishes to have a 15-20 percent contingency related to construction which is built into the budget transfer request just in case there are additional construction related costs.
SCHEDULE PROGRESS
Design Procurement Council - Design Design Construction Procurement Council - Construction Construction
 
SCHEDULE BREAKDOWN
 
Delivery Method:   Construction Manager @ Risk (CM@R)
PROJECT PHASES PERCENT COMPLETE ORIGINAL EST COMPLETION PROJECTED COMPLETION PROCUREMENT RESULTS
 
Design Procurement 100 %
 
Council - Design N/A
 
Design 100 %
 
Construction Procurement 100 %
 
Council - Construction Complete 5/28/2009 5/28/2009 Intergovernmental Agreement (IGA) Approval
 
Construction 75 % 8/15/2012 8/15/2012
BUDGET BREAKDOWN
FUNDING SOURCE General Capital and Sewer Operations
 
PROJECTED BUDGET Original $290,000.00
 
Change $0.00
 
Amended $290,000.00
 
TOTAL EXPENDED $243,015
 
BUDGET NOTES
Budget transfer from the Public Safety Building project 20219 ($80,000) and sewer operations ($210,000) June 11, 2009. Budget - FY09 - $243,000, FY10 - $100, FY11 - $46,900
PROJECT UPDATE
CURRENT PROJECT STATUS
Waddell Road was closed between Loop 303 and Sarival Avenue from June 2, 2010 – July 01, 2010. Traffic on Loop 303 will be temporarily shifted around the intersection. Detour: Westbound traffic on Waddell Road may use Reems Road to Cactus or Greenway roads to access Loop 303. Traffic on Loop 303 may use Cactus or Greenway roads to access Sarival Avenue
 
WHAT'S NEXT
SUNDT will remove manhole #9 on the east side on Cactus Road late summer or early fall. Two existing manholes on Cactus Road will remain and have to be adjusted to grade.
        
 

Official Seal of Surprise, AZ
Defining Vibrant, Southwest Living
16000 N. Civic Center Plaza   Surprise, AZ 85374   Phone: 623.222.1000   TTY: 623.222.1002 / Phone Directory