Monthly Capital Improvements Project Report
|
|
Click photo to enlarge |
|
RECREATION CAMPUS MONUMENT SIGN
|
| LAST UPDATED: |
11/9/2009
|
| PROJECT | 20920 |
| DEPARTMENT | PUBLIC WORKS - BUILDINGS |
| PROJECT MANAGER | Jeff Davidson |
| CONTACT NUMBER | 623.222.6000 |
| ADDRESS/LOCATION | Bell Road and Bullard Avenue |
PROJECT DESCRIPTION
Construction of a monument sign on Bell Road at the corner of Bell Road and Bullard Avenue, including an electronic message center using light emitting diode (LED) technology. The message sign will be used to convey information about events held at the recreation campus.
|
|
|
|
|
SCHEDULE PROGRESS |
|
Design Procurement |
Council - Design
|
Design |
|
|
Construction |
|
|
|
|
|
|
|
|
|
|
|
|
SCHEDULE BREAKDOWN |
Delivery Method:
Design - Build |
|
|
PROJECT PHASES |
PERCENT COMPLETE |
ORIGINAL EST COMPLETION |
PROJECTED COMPLETION |
PROCUREMENT RESULTS |
|
|
|
Design Procurement |
100
% |
10/10/2009 |
9/30/2009 |
|
|
|
|
Council - Design |
N/A
|
9/10/2009 |
5/28/2009 |
|
|
|
|
Design |
40
% |
12/1/2009 |
12/1/2009 |
|
|
|
|
Construction |
0
% |
2/1/2010 |
2/1/2010 |
|
|
|
|
|
|
|
|
FUNDING SOURCE |
General Fund |
|
|
|
PROJECTED BUDGET |
Original |
$100,000.00 |
|
|
|
|
Change |
$0.00 |
|
|
|
|
Amended |
$100,000.00 |
|
|
|
TOTAL EXPENDED |
|
$28,047 |
|
|
BUDGET NOTES
New project May 09. |
|
|
|
|
CURRENT PROJECT STATUS
This project is part of the overall Bullard Avenue widening project. The final aesthetic for the sign has been approved by city management and the sign vendor has begun drafting shop drawings for the fabrication of the sign. These shop drawings will also be submitted to the city for permit review. |
WHAT'S NEXT
The sign's shop drawings are anticipated to be completed in November. These drawings will be submitted to the City's Building Safety Division for permit review. |
|
|