Monthly Capital Improvements Project Report
|
|
|
|
BELL ROAD MONUMENT SIGN
|
| LAST UPDATED: |
8/3/2010
|
| PROJECT | 20921 |
| DEPARTMENT | PUBLIC WORKS - BUILDINGS |
| PROJECT MANAGER | Terry Lowe |
| CONTACT NUMBER | 623.222.6000 |
| ADDRESS/LOCATION | 12425 W. Bell Road |
PROJECT DESCRIPTION
Renovation of the city monument sign along Bell Road in front of the former city hall campus. The sign will include the street address, space for up to 6 tenants and an electronic message center using light emitting diode (LED) technology. Costs also include upgrades in electrical capacity.
|
|
|
|
|
SCHEDULE PROGRESS |
|
Design Procurement |
Council - Design
|
Design |
|
|
Construction |
|
|
|
|
|
|
|
|
|
|
|
|
SCHEDULE BREAKDOWN |
Delivery Method:
Design - Build |
|
|
PROJECT PHASES |
PERCENT COMPLETE |
ORIGINAL EST COMPLETION |
PROJECTED COMPLETION |
PROCUREMENT RESULTS |
|
|
|
Design Procurement |
50
% |
9/15/2009 |
|
Project On Hold |
|
|
|
Council - Design |
N/A
|
|
|
|
|
|
|
Design |
0
% |
10/30/2009 |
|
|
|
|
|
Construction |
0
% |
12/30/2009 |
|
|
|
|
|
|
|
|
|
FUNDING SOURCE |
General Fund |
|
|
|
PROJECTED BUDGET |
Original |
$100,000.00 |
|
|
|
|
Change |
$0.00 |
|
|
|
|
Amended |
$100,000.00 |
|
|
|
TOTAL EXPENDED |
|
|
|
|
BUDGET NOTES
New project June 09.
Budget - FY11 - $100,000 |
|
|
|
|
CURRENT PROJECT STATUS
The project team has submitted the selected sign rendering to the project stakeholders and to city management for approval. The team is awaiting approval and direction. Until approval and direction is provided the project is on hold. |
WHAT'S NEXT
Upon direction from stakeholders and city management, the project team will proceed. |
|
|